Futuro

CSDC Program: Turnkey Development Project
Las Vegas, NV

Type of Project:
Acquisition and renovation of a former grocery store located on 4.6 acres of land. In 2017, CSDC completed a New Markets Tax Credit financing for the acquisition and Phase I renovation. Since that time, CSDC has completed three additional phases of expansion and improvement to the property, providing nine additional classrooms, a health center, additional restrooms, SUP required offsite road improvements and other building enhancements. CSDC is currently in the design phase of the final expansion project, expected to be completed by July, 2021.

Grades Served: K-8

Square Footage: 50,000

Project Cost: $10,000,000

Delivery Date:
Ongoing – Phase IV anticipated completion in July 2021

Value Added Results:
Renovations planned and executed in 4 phases over 5 years to accommodate a slow growth school model, ensuring school affordability.